For Approval

For info

 

 

Proposed Budget 2023/24
£'000

Profiled Budget 2023/24
£'000

Total Budget 2023/24
£'000

Provisional Budget 2024/25
£'000

Provisional Budget 2025/26
£'000

Provisional Budget 2026/27
£'000

Provisional Budget 2027/28
£'000

Description

Programme Expenditure

 

 

 

 

 

 

 

 

Delivery of New Council Homes

 

 

 

 

 

 

 

 

Home Purchase Policy

15,000

1,000

16,000

10,000

4,500

2,650

 

Continued delivery of the Home Purchase Policy. 2023/24 budget would allow up to 60 properties. 40 properties in 2024/25 and 20 properties 2025/26 and 10 properties in 2026/27.

Other Acquisitions

 

5,205

5,205

                       

                     

                     

 

Budget for the purchase of properties outside of the Home Purchase Policy, where opportunities and business cases present
themselves.

Feasibility

350

 

350

300

200

                     

 

Feasibility budget required to bring forward the new supply pipeline.

Converting spaces in existing buildings

1,730

516

2,246

2,200

2,200

                     

 

Continued delivery of the Hidden Homes scheme where underutilised spaces are converted into new council homes.

Design Competition

682

1,625

2,307

                       

                     

                     

 

Previous budget approved for Frederick Street and Rotherfield Crescent profiled in the financial years to match the latest deliver programme.

Moulsecoomb Hub land

 

9,014

9,014

 

                     

                     

 

The appropriation is expected to take place during 2023/24. The November committee report requested further budget to bring the project up to the planning with final scheme and budget approval to be taken back to committee during 2022.The budget line reflects the approvals given to bring the scheme up to RIBA stage 3. Further detail can be found in the Housing Committee report from 22nd June 2022.

Windlesham Close

1,350

685

2,035

4,341

                     

                     

 

Approval given for this scheme at the 1st July 2022, the budget has been profiled to match the latest estimates of the cashflow.

Palace Place

                        

1,608

1,608

                     

                     

 

Approval given for this scheme at the 1st July 2022, the budget has been profiled to match the latest estimates of the cashflow.

Belgrave Day Centre, Portslade

934

                     

934

331

                     

                     

 

Purchase of 49 homes from HBH LLP at the Portslade site.

Coldean Lane, North of Varley Halls

6,160

(813)

5,347

857

                     

                     

 

Purchase of 127 homes from HBH LLP at the Coldean site. Final budget lines following the construction of homes during the previous financial years.

Total Delivery of New Council Homes

26,206

18,840

45,046

18,029

6,900

2,650

                     

 

Improving Housing Quality

 

 

 

 

 

 

 

 

Main Door Entry Systems & CCTV

817

 

817

700

700

700

700

Repair and replacement of Main Entrance Doors. Long term programme of door entry system replacements, as systems fail or reach the end of their serviceable life, with spare parts unable to be sourced. These two programmes are reviewed alongside each other and works coordinated where feasible to ensure value for money. Installation and upgrade of CCTV systems to increase security of blocks.

Water Tanks, Ventilation, Lighting & Lightning Protection & Fire Alarms

1,930

 

1,930

1,600

1,490

1,500

1,580

Projects help meet statutory requirements and ensure safety and welfare for residents through replacement and improvements.

Lifts

880

 

880

1,980

1,130

1,000

1,000

The lift replacement and upgrade programme is a long-term commitment to council residents. The majority of lifts have now been replaced since its inception, and the programme is under ongoing review to ensure it continues to provide good value for money.

Fire Safety & Asbestos Management

3,320

 

3,320

2,590

2,590

2,390

2,390

Effectively managing the risks of both fire and asbestos materials is an ongoing need. Includes both statutory requirements and provision for enhanced fire safety measures.  In particular, including provision for a programme of EWS1 surveys in 23/24.

Minor Capital Works

520

 

520

795

810

851

894

Investment in smaller capital repairs across the HRA stock as well as investing in car parks and garages.

Condensation & Damp Works

500

 

500

280

280

294

309

Health and welfare of council residents is assisted by tackling issues arising from condensation and damp in properties. The budget for 2023/24 has been increased following the tragic Rochdale Borough Homes case and will keep this budget under review.

Major Structural works

2,338

5,760

8,098

8,383

6,500

6,300

6,200

Meeting our landlord obligations through maintaining the structural and general external integrity of properties.

Major Empty Property works

220

 

220

220

220

220

220

Extensive refurbishment of empty homes prior to re-letting.

Cyclical Repairs & Decorations

1,384

 

1,384

1,605

1,188

1,247

1,309

External and common way repairs and decorations across the city help reduce ongoing costs and keep properties well maintained. Housing Investment and Asset Management team work closely with residents to ensure internal decorations in blocks are consistently delivered across the city.

Seniors Housing Improvements

330

 

330

330

330

200

200

Meets the identified need from November 2019 to invest in the council’s Seniors Housing schemes to improve security, accessibility and address any structural issues identified.  

Future capital projects

250

 

250

250

250

250

250

Specialist and other surveys to support future programmes.

Dwelling Doors

990

 

990

990

990

1,040

1,092

Replacing doors to properties with secure and efficient design helps residents feel safer. This programme includes the provision of fire-rated doors to dwellings where required.

Kitchens & Bathrooms

2,480

 

2,480

2,590

2,590

2,720

2,856

This budget helps to ensure homes comply with the Brighton & Hove Standard.

Rewiring - Domestic/ Communal

1,735

 

1,735

1,820

1,840

1,932

2,029

Safe and reliable and compliant electrical installations and efficient lighting are supported from this budget.

Windows

1,443

200

1,643

2,154

2,135

2,242

2,354

Window replacement programmes meet the council's landlord obligations, improve energy efficiency, warmth and reduce ongoing repair costs.

Roofing

1,223

 

1,223

1,205

1,100

1,155

1,213

Helps to extend the life of assets, improves insulation and reduces responsive repairs.

Sustainability & Carbon Reduction

                        

 

                       

                       

                     

 

 

 

Domestic/Communal Heating Improvements

2,230

 

2,230

2,530

2,640

2,772

2,911

Efficient and modern replacement heating systems improve thermal comfort, reduce carbon emissions and resident fuel costs.

Energy Efficiency & Low Carbon Heating

1,670

 

1,670

1,740

3,300

2,000

2,000

This programme will help take up a range of opportunities to further improve the energy rating of our homes and to identify projects that will help move towards zero carbon from our service delivery activities by 2030.

New Solar Panels Programme

440

800

1,240

1,540

1,540

1,000

1,000

Project Management support is now in place to deliver the solar PV programme, procurement of a new contract has begun and should be in place Spring 2023. We are planning a 3 year programme delivering up to 1000 new systems, budgets have been re-profiled on this basis.

Tackling Inequality

                        

 

                       

                       

                     

 

 

 

Environmental Improvements

625

100

725

360

360

360

360

This budget funds environmental and communal area improvement work based on resident priorities.
It also includes provision for the refurbishment of housing owned playgrounds (as reported to ETS Committee in January 2021).

Disabled Aids & Adaptations

1,600

 

1,600

1,600

1,600

1,600

1,600

Enabling vulnerable residents to continue to live independently in their homes through investment in housing adaptations.

Conversions & Extensions

660

 

660

700

730

750

750

Tackling overcrowding across the city is of key importance to ensure good quality housing.

Total Investment in existing Housing Stock

27,585

6,860

34,445

35,962

34,313

32,523

33,217

 

Total Other Projects

250

                      

250

250

100

100

100

 

Total Programme

54,041

25,700

79,741

54,241

41,313

35,273

33,317

 

Programme Funding

 

 

 

 

 

 

 

 

Revenue Contribution to investment in existing housing stock

19,358

19,358

18,949

20,096

18,614

18,901

24/25 to 27/28 figures are illustrative and will be adjusted accordingly as the 30 year business plan is updated.

Borrowing

28,035

20,872

48,907

26,760

19,687

15,864

14,416

Borrowing required to fund capital investment.

HRA reserves

1,090

 

1,090

4,800

 

 

 

Useable revenue and capital reserves.

Capital Receipts

750

                     

750

                       

                     

 

 

Capital receipts for use against new housing delivery.

RTB Receipts

2,028

1,074

3,102

2,652

1,350

795

 

Retained RTB receipts for New Build.

Energy Grants/FITs

180

 

180

180

180

 

 

Funding received to support sustainability and carbon projects.

Grant Funding

                        

2,649

2,649

                       

 

 

 

Land Release Funding grant received and Homes England grant for the purchase of HBH LLP Properties.

Commuted Sums

1,800

300

2,100

900

 

 

 

Funding to support the purchase of properties through the Home Purchase Policy.

Leaseholder Income

800

 

800

 

 

 

 

 

Earmarked rent reserve

 

805

805

 

 

 

 

 

Total Funding

54,041

25,700

79,741

54,241

41,313

35,273

33,317